Waters Protection Ordinance
(WPO)

English is not an official language of the Swiss Confederation. This translation is provided for information purposes only and has no legal force.

of 28 October 1998 (Status as of 1 January 2021)


Open article in different language:  DE  |  FR  |  IT
Art. 41 f Planning remediation measures for hydropeaking

1 The can­tons shall sub­mit to the FOEN a plan for meas­ures to re­medi­ate hy­dro­power plants that cause hy­dropeak­ing in ac­cord­ance with the pro­ced­ure de­scribed in An­nex 4a num­ber 2.

2 The per­sons re­spons­ible for hy­dro­power plants must grant ac­cess to the au­thor­ity re­spons­ible for the plan and provide the re­quired in­form­a­tion, in par­tic­u­lar on:

a.
the co­ordin­ates and the des­ig­na­tion the in­di­vidu­al parts of the plant;
b.
the flow rates of the wa­ter­course con­cerned with meas­ured val­ues at in­ter­vals of no more than 15 minutes (hy­dro­graph) over a peri­od cov­er­ing the past five years; If these meas­ured val­ues are not avail­able, the hy­dro­graph may be cal­cu­lated us­ing data re­lat­ing to hy­dro-elec­tric power pro­duc­tion at the plant and the wa­ter flow;
c.
the meas­ures car­ried out and planned to re­duce the ef­fects of hy­dropeak­ing;
d.
the avail­able res­ults of the study on the ef­fects of hy­dropeak­ing;
e.
the planned struc­tur­al and op­er­a­tion­al changes at the plant.