Art. 41 g Remediation measures for hydropeaking
1 Based on the measures plan, the cantonal authority shall order the remediation of hydropeaking and require the persons responsible for hydropower plants to examine various types of remediation measure in order to implement the plan. 2 Before it decides on the remediation project, it shall consult the FOEN. With a view to an application under Article 30 paragraph 1 of the Energy Ordinance of 1 November 201761 (EnO), the FOEN shall verify whether the criteria of Annex 3 number 2 EnO are met.62 3 The persons responsible for hydropower plants shall verify the effectiveness of the measures taken as required by the authority. 62Second sentence amended by Annex 7 No II 2 of the Energy Ordinance of 1 Nov. 2017, in force since 1 Jan. 2018 (AS 2017 6889). |