Art. 42a Serious harm due to change in the bed load budget 66

A change in the bed load budget causes ser­i­ous harm to the in­di­gen­ous flora and fauna and their hab­it­ats if in­stall­a­tions such as hy­dro­power plants, gravel ex­cav­a­tion sites, bed load traps or river con­trol struc­tures al­ter the mor­pho­lo­gic­al struc­tures or the mor­pho­lo­gic­al dy­nam­ics of the wa­ters to their det­ri­ment.

66 In­ser­ted by No I of the O of 4 May 2011, in force since 1 June 2011 (AS 2011 1955).