Art. 42b Planning the measures to remediate the bed load budget 67

1 The can­tons shall sub­mit a plan to the FOEN of their meas­ures to re­medi­ate the bed load budget in ac­cord­ance with the pro­ced­ure de­scribed in An­nex 4a num­ber 3.

2 The per­sons re­spons­ible for in­stall­a­tions must al­low ac­cess to the au­thor­ity re­spons­ible for the plan and provide the re­quired in­form­a­tion, in par­tic­u­lar on:

a.
the de­tails and the des­ig­na­tion of the in­stall­a­tions and in the case of hy­dro­power plants the in­di­vidu­al parts of the in­stall­a­tion;
b.
how the bed load is dealt with;
c.
the meas­ures car­ried out and the planned in or­der to im­prove the bed load budget;
d.
the avail­able res­ults of the study of the bed load budget;
e.
the planned struc­tur­al and op­er­a­tion­al changes to the in­stall­a­tion.