Art. 53 Consultation, publication and public inspection

1 After re­ceiv­ing an ap­plic­a­tion, the Fed­er­al Of­fice shall for­ward it to the can­ton­al au­thor­it­ies con­cerned and re­quest them to sub­mit an ad­vis­ory opin­ion with­in three months. The Fed­er­al Of­fice may ex­tend the dead­line in cer­tain jus­ti­fied cir­cum­stances.

2 The ap­plic­a­tion shall be pub­lished in the of­fi­cial gaz­ette of each can­ton and com­mune con­cerned, as well as in the Swiss Fed­er­al Gaz­ette, and made avail­able for pub­lic in­spec­tion for a peri­od of 30 days.

3 ...18

18 Re­pealed by An­nex No 11 of the FA of 19 June 2020, with ef­fect from 1 Jan. 2021 (AS 2020 4085; BBl 2018 4713).