Art. 74Deadlines for dealing with applications
The following deadlines generally apply for dealing with applications for licences and approvals in accordance with Articles 49 to 63 of the Nuclear Energy Act:
a.
from date of receipt of complete application until it is passed on to the cantons and federal authorities concerned, or until publication and presentation for public consultation: one month;
b.
from completion of instruction procedure until a decision is taken: six months.