Art. 366
3. Prompt commencement and contractual performance of work 1Where the contractor fails to commence the work on time or delays its performance in breach of contract or, through no fault of the customer, falls so far behind that there is no longer any prospect of completing the work on time, the customer is entitled to withdraw from the contract without waiting for the agreed delivery date. 2Where during the course of the work it becomes evident that, through the fault of the contractor, the work will be performed in a manner that is defective or otherwise contrary to the agreement, the customer may set or have the court set the contractor an appropriate time limit within which to take remedial action and notify him that any failure to do so will result in the hire of a third party to take such remedial action or to complete the work at the risk and expense of the contractor. |