Art. 373

2. Amount of pay­ment

a. Firm com­mit­ment

 

1 Where the pay­ment was fixed in ad­vance as an ex­act amount, the con­tract­or is ob­liged to per­form the work for the agreed amount and may not charge more even if the work en­tailed more la­bour or great­er ex­pense than pre­dicted.

2 However, where per­form­ance of the work was pre­ven­ted or ser­i­ously hindered by ex­traordin­ary cir­cum­stances that were un­fore­see­able or ex­cluded ac­cord­ing to the con­di­tions as­sumed by both parties, the court may at its dis­cre­tion au­thor­ise an in­crease in the price or the ter­min­a­tion of the con­tract.

3 The cus­tom­er must pay the full price even where the work has en­tailed less la­bour than pre­dicted.

 