Art. 378

IV. Im­possib­il­ity of per­form­ance for reas­ons at­trib­ut­able to the cus­tom­er

 

1 Where com­ple­tion of the work is rendered im­possible by chance oc­cur­rence af­fect­ing the cus­tom­er, the con­tract­or is en­titled to pay­ment for the work already done and of ex­penses in­curred that were not in­cluded in the price.

2 Where the cus­tom­er is at fault for the im­possib­il­ity of per­form­ance, the con­tract­or may also claim dam­ages.

 