Art. 107
4. Withdrawal and damages a. Subject to time limit 1 Where the obligor under a bilateral contract is in default, the obligee is entitled to set an appropriate time limit for subsequent performance or to ask the court to set such time limit. 2 If performance has not been rendered by the end of that time limit, the obligee may compel performance in addition to suing for damages in connection with the delay or, provided he makes an immediate declaration to this effect, he may instead forego subsequent performance and either claim damages for non-performance or withdraw from the contract altogether. |